15
Table 3 - Project Milestones
Date
Milestones
April 1
Project Charter signed by Chief Operations Officer, endorsed by CEO, Project Manager formally appointed.
April 1
Project Planning Begins.
April 22
Project planning ends, Project Kick-off and Execution starts, vendor and contract selection start.
June 1
Standardized Intake Forms and Digital Processing development begins under the Agile and Scrum Framework
June 15
Build out the DOTS API integration with the new forms
July 1
Minimum Viable Product (MVP) Reached, MVP testing starts, Onboarding Suspension Service Centers.
July 1
Phased Employee Training and Development Begins
July 15
Launch Features Completed, MVP testing completed, Training completed
August 1
Digital Processing Forms Launch, Project Ends, Agile and Scrum development continues.
2025 Q3
Additional features update v1.1, launch Employee Survey
2025 Q4
Additional features update v1.2, Collect Survey Data for features update v1.3/v1.4 in Q1/Q2
Table 4 - Decision Matrix
Criteria: Worst=1, Good=2 and Best=3
Potential Solutions
Cost
Implementation time
Feasibility Long-term impact
Scalability
Standardized Inventory Management Standardization and Digital Processing
1
1
3
3
3
2.6
2
3
3
2.2
Centralized Packing & Shipping Station
1.3
2
2
2.3
2